Change orders, explained
What is a change order in construction?
A change order is a written, signed change to your construction contract. It says what’s changing in the work, and what that does to the price and the finish date.
Or call or text (817) 631-9803
From AIA Contract Documents, the American Institute of Architects’ contract publisher, read November 27, 2026.
Or call or text (817) 631-9803
From AIA Contract Documents, the American Institute of Architects’ contract publisher, read November 27, 2026.
The definition
What a change order means
A change order is how a construction contract gets changed once it’s signed. It records the change in the work, and any change to the price or the schedule. Once everyone who signed the contract signs it, it becomes part of the contract.
A construction change order is a written agreement among the owner, contractor, and architect that changes the work, contract sum, contract time, or any combination.
Matt Viator, Assistant General Counsel, AIA Contract Documents · read November 27, 2026
What a change order records
- What’s changing in the work
- The change to the price, if any
- The change to the finish date, if any
“If any” matters. A change order can lower the price, add to it, or change nothing but the work itself. When there’s no architect on the contract, it’s you and the builder who sign.
The causes
What causes change orders
A change order doesn’t mean someone made a mistake. Most come from one of the six causes below.
-
You change the plan.
A different layout, a bigger window, one more outlet.
-
The house hides something.
Rot, old wiring or a pipe behind a wall, or something in the ground.
-
A product changes.
A substitute for something that’s no longer made or can’t be had in time.
-
An allowance gets settled.
The finish you picked cost more or less than the amount the contract set aside for it.
-
Something outside anyone’s control.
Weather, or a shipment that doesn’t arrive.
-
The drawings missed something.
A gap or an error in the plans.
Who pays for a change depends on the contract, and on whether you got something you hadn’t already paid for.
The comparison
Change order vs. change directive vs. minor change
A change order is the usual way, but not the only one. When work can’t wait for a price, a change directive lets it go ahead. When a change is small and doesn’t move the price or the date, a minor change covers it.
| What it covers | Change order | Change directive | Minor change |
|---|---|---|---|
| When it’s used | Everyone has agreed on the change, its price and its time | The work has to go ahead before the price or time is agreed | A small change that fits the plans’ intent |
| Who signs | Everyone who signed the contract | The owner, and the architect if there is one. The builder goes ahead while the price is worked out | The architect alone |
| Does the price or date move? | Yes, if the change order says so | It can, once it’s worked out. If the builder agrees, it becomes a change order | No |
The American Institute of Architects publishes standard forms for each: G701 for a change order, G714 for a change directive and G710 for a minor change.
The process
How the change order process works
Most change orders follow the same six steps, from the first request to the last signature.
- 01
Someone asks for a change.
You do, the builder does, or the plans need an answer nobody had.
- 02
The change gets written down.
What’s changing, and which drawings or specs it touches.
- 03
The builder prices it.
The cost, and any time it adds, on the terms your contract sets.
- 04
You review it.
Is it really new work? Do the price and the time make sense?
- 05
Everyone on the contract signs it.
Before the changed work starts, unless a change directive let it go ahead.
- 06
It becomes part of the contract.
The new work, price and date replace the old ones.
Before you sign
What to check before you sign a change order
A change order is part of your contract once you sign it. Six checks, before you do.
-
It’s in writing, and no work started on a spoken yes.
-
It says exactly what’s changing, and which drawings it touches.
-
It isn’t charging you for work your contract already covers.
-
It states the new price and the new finish date, even if neither moves.
-
The price follows the method your contract sets.
-
Anything attached to it is listed and dated.
By contract
Change orders on a fixed-price or cost-plus contract
A change order works the same way under both. What it moves is different.
Fixed price
The price is set, so a change order is how it changes. Each change gets its own price before the work.
Cost-plus
The work is billed at what it costs, so a change order records what’s changing, the time it adds, and any change to the fee the contract allows. If the contract has a maximum price, the change order is what moves it.
At 6th Ave Homes
How to have fewer change orders
AIA’s own article says design-build generally produces fewer change orders, because the people building are involved while the design can still change. Finish the design before the price, and make your choices early. We design, draft and build under one roof, and we bill Cost Plus.
How a job runs with us:
- Step 1
A designer and a builder walk your house with you and give you an estimate, at no charge.
- Step 2
After the design, you get a detailed budget.
- Step 3
The build is billed at cost, plus one markup you can see. Open receipts: you see what we paid.
Questions
Questions about change orders
Planning a project? Talk to us before the design is set.
Who signs a change order?
Everyone who signed the contract. On a job with an architect on the contract, that’s the owner, the builder and the architect. On a house with no architect on the contract, it’s you and the builder. Your signature is what makes the change part of the contract.
Can a builder start the changed work before the change order is signed?
Only if the contract allows it, usually through a change directive: a written order to go ahead while the price and time get worked out. Work that starts on a spoken yes, with nothing in writing, is the kind that ends in an argument about what was agreed.
Does a change order always cost more?
No. A change order can add to the price, lower it with a credit, or change the work without moving the price or the date at all.
Who pays when something is found behind a wall?
Your contract decides. It turns on what the contract says about conditions nobody could see, and on whether you got something you hadn’t already paid for. Where an architect drew the plans and missed something, it can also turn on whether the architect took reasonable care.
Do change orders have to be in writing in Texas?
The Texas Real Estate Commission’s contract for a new home being built requires change orders in writing. Other contracts set their own rules, so read yours. Here’s what a Texas new-home contract says.
What’s an ASI in construction?
Architect’s supplemental instructions. It’s how an architect orders a minor change, or clears up a detail, without changing the price or the finish date. If the builder thinks an ASI does move either one, the builder should say so before doing the work.
How do you avoid change orders?
You can’t rule them out, because a house can hide things. You can have fewer: finish the design before the price, make your choices early, and hire a team that builds what it designs. Here’s what design-build means.
The definitions on this page are quoted or summarized from AIA Contract Documents, read November 27, 2026. This explains the terms. It isn’t legal advice about your contract.
Best Home Builder & Remodeler
Fort Worth MagazineFort Worth Chamber Small Business of the Year4.7 stars from 91 Google reviews as of September 2026
Your project
Plan the changes before the build starts
Bring a wish list or plans you already have, and start with an honest estimate. No charge, no obligation.
Or call or text (817) 631-9803
