Contingency, explained

What is a construction contingency?

A construction contingency is money set aside in a construction budget for costs nobody can see yet, like rot or old wiring behind a wall. Our cost pages put it at 10 to 20 percent of the budget, depending on the job.

Or call or text (817) 631-9803

Sources: the American Institute of Architects, Ogletree Deakins and ConsensusDocs, read November 27, 2026.

Two homeowners standing in their living room, opened to the studs, with the fireplace stone pulled down at their feet.

The definition

What a contingency is for

A contingency covers the costs a budget can’t name ahead of time: what’s behind a wall, under a floor or in the ground. It’s set aside before the work starts.

The architects’ definition

A contingency is a predetermined amount or percentage of the contract held for unpredictable changes in the project.

David H. Hart, FAIA, the American Institute of Architects, November 30, 2023 · read November 27, 2026

What it’s there for

  • Old wiring that isn’t up to code
  • Plumbing that needs replacing
  • Framing that has been compromised
  • Water damage from a leak nobody knew about
  • Limestone close to the surface, or clay that calls for engineered piers

Nobody can see through walls before demo.

Spending it on upgrades

You can spend your own contingency on an upgrade you choose along the way. Every dollar that goes to a better tile, though, is a dollar that isn’t there when something’s found.

How a contingency differs from an allowance

Three of our team measuring a window wall in a remodel opened to the studs, with the pipes, wiring and insulation behind the wall in view.

How much to hold

How much construction contingency to hold

What to hold depends on the kind of job. These are the ranges from our own cost pages, as a share of the project budget. The jobs that open up the most of a house that’s already standing, a whole-home remodel or an addition, carry the most.

  1. Kitchen remodel

    10 to 15 percent of the budget

  2. Primary bath remodel

    10 to 15 percent of the budget

    for what is behind the walls

  3. Garage apartment or ADU

    10 to 15 percent of the budget

    and more on a conversion, where demolition turns up the surprises

  4. Pool and outdoor living

    10 to 15 percent of the budget

  5. Custom home

    10 to 15 percent of the budget

  6. Home addition

    15 to 20 percent of the budget

    for what the existing house turns out to be hiding

  7. Whole-home remodel

    15 to 20 percent of the budget

    on a down-to-studs remodel, we would not go lower

The whole-home and addition rows run highest for the reason our whole-home cost guide gives: the most expensive surprises in an older house are behind the walls, and nobody can see them until the walls are open.

Our figures, from our own service pages, read November 27, 2026. Our published cost ranges are construction plus our fee, before permits and contingency, so the contingency goes on top of them.

The math, on a round number

Say a budget is $100,000. That’s a round number to show the math, not a price, ours or anyone’s. At 10 to 15 percent, you’d hold $10,000 to $15,000 on top of it. At 15 to 20 percent, the same budget would hold $15,000 to $20,000.

Who controls it

Owner’s contingency vs. contractor’s contingency

There are two kinds, and the difference is whose money it is to spend. An owner’s contingency is yours, set aside in your budget. A contractor’s contingency is built into the builder’s price, for risks the builder carries.

Owner’s contingency

Whose it is
Yours. It sits in your budget.
What it’s for
Changes you choose, and risks that are yours to carry. Ogletree: “additions to the project’s scope or owner’s risk items.”
How it gets spent
Through change orders you sign. ConsensusDocs: it “is typically used to fund change orders.”

Contractor’s contingency

Whose it is
The builder’s. It’s inside the price.
What it’s for
The risks the builder is responsible for. Ogletree: it “exists to mitigate project-related risks for which the contractor is responsible.”
How it gets spent
By the builder. On a contract with a maximum price, ConsensusDocs says the contingency fund “is available only for the contractor’s use, not the owner’s.”

Fixed price

Any contingency the builder carries is inside the one amount you agreed to. If it isn’t needed, the price doesn’t come down unless your contract says so.

Cost-plus

You pay what the work costs, so the contingency is room in your budget, spent only when the work calls for it. You can ask to see what it goes to.

Cost-plus with a maximum price

A contractor’s contingency inside the cap is the builder’s to spend, per ConsensusDocs. The contract should say what happens to what’s left.

At the end of the job

What happens to contingency you don’t use

Your contract decides.

Any unspent contingency funds at the end of the project typically revert to the owner or are shared.

Randolph E. Ruff, Ogletree Deakins, May 24, 2017 · read November 27, 2026

When it’s split, the contract calls it shared savings. ConsensusDocs: “any leftover contingency will be split, according to some predetermined allocation, between the contractor and the owner.”

ConsensusDocs, November 3, 2023 · read November 27, 2026

Five questions to ask before you sign

  1. Whose contingency is it?

    Yours, the builder’s, or one of each. The contract should name it.

  2. Is it inside the price, or on top of it?

    Find the line in the bid or the contract, and ask whose it is.

  3. Who decides when it gets spent?

    Ask to see every cost that comes out of it, in writing, before the work goes ahead.

  4. What happens to what’s left?

    Back to you, split, or kept. Get the answer in the contract.

  5. What happens if it runs out?

    Ask who pays past it, and whether there’s a maximum price.

  6. If the contract doesn’t say whose contingency it is, you’ll find out the day the walls come open.

When the walls come open

How a contingency turns into a change order

When something’s found, the fix gets priced and written up, usually as a change order. With an owner’s contingency, that change order is paid out of it, and the total you planned holds as long as the contingency covers it.

  1. Something’s found.

    Rot, old wiring or a pipe behind a wall, or something in the ground.

  2. It’s priced and written up.

    As a change order you read and sign before that work goes ahead.

  3. The contingency pays for it.

    What’s left in it goes down by that much.

If it runs out, the next change order adds to the total. That’s why the ranges above climb on the jobs that open more of the house.

An owner’s contingency “is typically used to fund change orders.” ConsensusDocs, November 3, 2023 · read November 27, 2026

A finished kitchen with white cabinets, a stone slab behind a range with brass knobs, and a pot filler.

At 6th Ave Homes

How a contingency works with us

When the walls turn something up, there’s room in the budget to deal with it, instead of a surprise you weren’t planning for.

With Cost Plus billing, anything the house turns up is priced in the open. And because Cost Plus bills the work that actually gets done, contingency the house never calls for is never spent.

After we walk the house you get an estimate, and when the design is done you get a detailed budget, so you plan around a real budget and see what we paid as the work goes.

Questions

Questions about construction contingency

Planning a project? Talk to us before the design is set.

What is a contingency in construction?

It’s an amount in a construction budget held back for the costs nobody can predict, so something found behind a wall doesn’t stop the job or blow up the budget.

What is a good contingency percentage for a remodel?

Our cost pages put it at 10 to 15 percent of the budget for a kitchen or a primary bath, and 15 to 20 percent for a whole-home remodel or an addition, where more of the house gets opened up.

How much contingency should a new house have?

Our cost pages put it at 10 to 15 percent of the budget for a custom home.

Is the contingency included in the price?

It depends whose it is. A contractor’s contingency is built into the builder’s price. An owner’s contingency sits on top of it, in your budget.

Who controls the contingency?

You control an owner’s contingency, through the change orders you sign. A contractor’s contingency is the builder’s to use.

What happens to unused contingency?

It depends on the contract. It usually goes back to the owner, or gets split between the owner and the builder as shared savings. On a fixed price, any contingency the builder carries is already inside the one amount you agreed to.

Can I use the contingency for upgrades?

If it’s your contingency, you can. Every dollar spent on an upgrade is one less for what you find later.

Is a contingency the same as a change order?

No. The contingency is the money set aside. A change order is how a cost gets written up and added to the contract, and with an owner’s contingency, that’s often where the money comes from.

What goes in a construction budget besides the work?

Permits and a contingency. Both sit on top of our published ranges, which cover construction plus our fee.

The definitions on this page are quoted from the American Institute of Architects, Ogletree Deakins and ConsensusDocs, read November 27, 2026. This explains the terms. It isn’t legal advice about your contract.

4 years running

Best Home Builder & Remodeler

Fort Worth MagazineFort Worth Chamber Small Business of the Year4.7 stars from 91 Google reviews as of September 2026

Your project

Plan the budget with room in it

Bring a wish list or plans you already have, and start with an honest estimate. No charge, no obligation.

Start your project