Steps to building a custom home in order, in Fort Worth

Nine steps, from walking the lot to the City’s building final, and what your lot allows is settled before anything is drawn.

The order

The steps to building your own house, in order

Plan it, permit it, build it. The first five steps happen before anything is built, and the City inspects the house at each stage after that.

Two of our team looking over plans on a pickup tailgate in front of a brick house under a live oak

Plan it

Steps 01–03

  1. Step 01: Walk the lot with us

    We walk the lot with you, talk through how you actually live, and put numbers around what the site and the city will allow before anybody falls in love with a plan.

    The cheapest time to walk away. We find out whether the lot fits the house you want and whether the trees can stay.

    City of Fort Worth

    Fort Worth’s tree ordinance doesn’t apply to a single lot under an acre with one house or a duplex on it, unless your lots in that block add up to an acre.

  2. Step 02: Find out what the lot allows

    Zoning sets how far the house sits from each lot line, and the plat on record sets the lot itself.

    City of Fort Worth

    In the A-5 and A-7.5 districts, a house has to sit at least 5 feet from the side and rear lot lines and 20 feet from the front, or 15 on a limited local street.

    A house on the lot already? Spend an hour on it with us before anybody draws anything.

    Fort Worth setback requirements

    Remodel or rebuild

  3. Step 03: Draw the house, then price it

    Our drafting team draws the house, and we price it, permit it and build it.

    You make the biggest decisions on paper, while changes are still free.

    An outside engineer does the structural engineering.

    When the design is done, you get a detailed budget, built from the drawings.

    How we draw custom floor plans

Our 3D drawing of a new two-story house with a covered front porch and a side garage, before it was built
Step 03: our 3D drawing of a new house, before it was built.

Permit it

Steps 04–05

  1. Step 04: Gather what the City asks for

    The permit for a new house or an addition starts with your plat.

    The City also asks for a site plan and an engineered foundation plan. In the City’s words:

    “All new residential permits must have an engineered foundation plan.”

    Adding conditioned space or lighting adds energy code compliance documents.

  2. Step 05: Apply, pay the City’s fees, then the permit is issued

    City of Fort Worth

    The City’s standard is 7 business days to first review comments on a complete application. If the comments ask for changes, the plans are revised and reviewed again.

    Fort Worth charges each new house one-time impact fees for water and wastewater, and can add a transportation impact fee in 19 of its 28 service areas.

    If there’s a house on the lot

    It comes down under its own razing permit, separate from the new house’s building permit.

    A teardown carries demolition, disposal and often a utility disconnect the empty lot never sees.

Build it

Steps 06–09

Inspection card

City of Fort Worth · residential new building permit

  1. Step 06: Stake out, then the foundation

    City inspection

    Once the permit is issued, the City’s stakeout inspection (105) checks that the house sits in the right place on your lot. Underground plumbing and electrical are inspected next, then the foundation (115), all before concrete is poured.

    Building on clay soil in Fort Worth

  2. Step 07: Framing and rough-ins, inspected before the walls close

    You walk through the frame, and it’s the last easy chance to move a wall.

    City inspection

    The City inspects the sheathing, then the rough-ins, then the framing (110) once the rough-ins are approved.

  3. Step 08: Insulation, then the finishes

    City inspection

    Insulation is checked against your energy code compliance report before the walls close.

    We lock your selections long before this stage, so the finishes go in without holding up the schedule.

  4. Step 09: Final inspections, then the keys

    City inspection

    The trade finals come first: electrical (200), mechanical (300) and plumbing (400) finals, then the building final (100), once every related permit is final.

    We walk the house together. You list anything that needs fixing, and we fix it. Then you get the keys.

A living room with a floor-to-ceiling black and white marble fireplace, a black glass-front cabinet and white armchairs

Why the order matters

What goes wrong when building steps happen out of order

A step taken out of order costs you time or money later. It happens in three places.

Two of our team sitting on a bench inside a new house’s framing, reading the plans together

Buying the lot before anyone checks it

A lot is easy to fall for. Before you buy a lot, our construction team can tell you what’s actually buildable on it.

Drawing a house for no particular street

The size, roofline and front of a new house have to fit the street, and finishes cannot fix that later.

Designing with no price attached

Hire the designer and the builder separately, and it goes like this: You hire an architect who designs the house but doesn’t price it. You hire a builder who prices the drawings and comes back high. The drawings change to fit a budget the architect never saw.

City of Fort Worth

What the City of Fort Worth charges and checks on a new house

Eight things, each with its own rule. Here’s each one, and the guide that explains it.

What the City of Fort Worth charges and checks on a new house, the City’s rule for each, the step it belongs to, and the guide that explains it
Step 01 The trees Over an acre, a permit comes before any tree 6 inches or larger comes out. The tree ordinance
Step 04 Your lot’s plat Item 1 on the City’s checklist is a copy of your lot’s legally registered and recorded plat, from the Tarrant County courthouse. Replat requirements
Step 05 The old house The City calls it a residential razing permit, and you need one for each building you remove. Demolition permits
Step 05 The house itself Fort Worth prices a new house or an addition by its new square feet. Building permit fees
Step 05 Water and sewer The water and wastewater impact fees are collected before the permit is issued. No fees, no permit. Impact fees
Step 06–09 Wiring, plumbing, heating and air “Aside from your building permit, you still must obtain all trade permits that are needed separately and schedule inspections as required for each permit type.” The permit process
Step 06–09 The driveway and sidewalk at the street A new or repaired driveway approach or sidewalk sits in the City’s parkway, and it takes a parkway permit pulled by a bonded contractor. Driveway permits
Step 09 The end of the job The City of Fort Worth says a single-family house used only as a home isn’t required to get a certificate of occupancy. Certificate of occupancy

The City’s pages, read November 5 to 8, 2026.

A vaulted bedroom with tall white drapery on black rods and a painting over an antique settee

Time and cost

How long building a custom home takes, and what it costs

Plan on 11 to 18 months for a custom home with us.

Custom homes with us run $550,000 to $2,000,000, construction plus our fee, before permits and contingency: roughly 2,100 square feet at the low end, past 4,000 at the top. Permits on our builds run $3,000 to $5,000, and we plan a contingency of 10 to 15 percent of the budget.

See what a custom home costs in Fort Worth

Who runs the steps

One company runs every step of your build

Our drafting team draws your house. Our design team specs it. Our crew builds it.

Design, drafting and construction under one roof make us Fort Worth’s only one-stop shop.

We bill Cost Plus, so you see the real cost of materials and labor plus a transparent markup.

These nine steps sit under the three we name on every project: Meet Up, Team Up, Glasses Up.

Two of our designers comparing tile, hardware and flooring samples over a plan at a kitchen island

Questions

Questions about the steps to building a house

What is the first step in building a new house?

Walking the lot with a builder before you buy it or draw anything, so you know what zoning, setbacks and the trees allow.

What does the City of Fort Worth need before it issues a permit for a new house?

An application and a complete set of plans, with a copy of your lot’s recorded plat, a site plan and an engineered foundation plan. Adding conditioned space or lighting adds energy code compliance documents. The water and wastewater impact fees are paid before the permit is issued.

Can work on a new house start before the permit is issued?

No. The City won’t schedule an inspection until the permit is in issued status, and the first one is the stakeout.

What gets inspected when a new house is built in Fort Worth?

The stakeout checks where it sits. Then come the underground plumbing and electrical and the foundation, before concrete is poured; the sheathing, the rough-ins and the framing; the insulation, before the walls close; and the electrical, mechanical and plumbing finals, with the building final last.

How long does each step of building a house take?

We don’t publish a length for each step, because it depends on the house and the lot. Plan on 11 to 18 months for a custom home with us. How long a remodel or a new house takes

When does the old house come down on a teardown?

Before the new house starts, under its own razing permit: the City asks for one for each building you remove, and the new house takes its own building permit.

Other projects: kitchen remodel steps, bathroom remodel steps and home addition steps.

4 years running

Best Home Builder & Remodeler

Fort Worth MagazineFort Worth Chamber Small Business of the Year4.7 stars from 91 Google reviews as of September 2026

Your custom home

Start with your lot

Building a new home shouldn’t feel overwhelming.

We walk your lot with you, and you leave knowing what it allows and what comes next.

Walk your lot with us